EDUCATIONAL PROJECTS

S.N Name of Work Place & State Time in which completed Date of completion Principal features
1 Sports Complex Officers Club Satara 9 Months Feb. 2005 Sports Complex
2 School Building at Hanumangiri Vidyalaya Pusegaon Pusegaon Dist. Satara 10 Months Jan. 2006 School Building
3 Azad College Sadar Bazar 6 Months June 2006 College Building
4 Dahiwadi College Dahiwadi 6 Months Oct. 2006 College Building

BUILDERS & DEVELOPERS PROJECT

S.N Name of Work Place & State Time in which completed Date of completion Principal features
1 Kalyan Park Aprt. Trimurti Builders & Developers Godoli, Satara 13 Months Dec. 2002 Commercial & Residencial Building
2 Viay Millenium Vijay Developers Sadar Bazar , Satara 15 Months June 2005 Commercial & Residencial Building
3 Aditya Residency Aditya Builders & Developers Gendamal Satara 12 Months Dec.2005 Row Housing Scheme
4 Vaidya Villa Aprt. Landmark Developers Yadogopal Peth Satara 9 Months Sept. 2006 Commercial & Residencial Building
5 Kapila Park Aprt. Ashoka Group Builders & Developers Sadar Bazar, Satara 15 Months Dec.2006 Commercial & Residencial Building

COMMERCIAL & HOTEL PROJECT

S.N Name of Work Place & State Time in which completed Date of completion Principal features
1 Rest House for Maji Sainik Kalyan Karyalaya Raviwar Peth Satara 1 Year Feb 2004 Rest House Building
2 Hotel Sagar Delux Radhika Road Satara 2 Year Dec. 2004 Hotel Building
3 Kalyan Resort M.I.D.C. Satara 8 Months July 2006 Hotel Building
4 Kanse Dhaba National Highway, Satara 6 Months Dec. 2006 Hotel Building

WORK IN PROGRESS

S.N Name of Work Place & State Time in which completed Date of completion Principal features
1 Factory Building for Kavitsu Transmissions Ltd. M.I.D.C. Satara 15 Months March 2007 Industrial Project
2 Hospital Project for Shri.Barkade Radhika Road Satara 12 Months March 2007 Hospital Building
3 Factory Building Cyclo Transmissions Pvt.Ltd. Pathkalmatha, Satara July 2007 Dec.2005 Industrial Project
4 Residential Bungalow for Ghule Brothers Godoli Satara 12 Months Sept. 2007 Residential
5 Hotel Project for Cyclo Group Radhika Road, Satara 30 Months Dec. 2008 Hotel Project